Projects

Past performance.

Rainier Dynamics is a subcontractor to a regional paving contractor, May 2026 to present.

  • May 2026 to present

    Seattle/Puget Sound right-of-way restoration

    Subcontractor to a regional paving contractor.

    Work orders
    72 work orders
    Place
    Seattle/Puget Sound right-of-way
    Volume
    About 17,500 SF of concrete, 900+ LF of curb, 33 on prevailing wage

    Street panel removal and replacement, sidewalks, driveway approaches, curb and gutter, and utility restoration, with associated removal and site preparation.

    • Concrete sidewalk and hydrant pad marked for removal, with sawcut lines around the hydrant.
      Before: hydrant pad and sidewalk marked for removal.
    • Finished concrete hydrant pad and sidewalk panels, with the hydrant set in the new pad.
      After: finished hydrant pad and sidewalk panels.